Planned Power Outage: May 11, 15, & 17

Submitted

Posted on Thursday, May 10, 2018


Real Property Operations Detachment Petawawa will be conducting planned electrical power shut-downs on 11, 15 and 17 May 18 in order to perform upgrades to Garrison high voltage distribution infrastructure.  The shut-downs will be 0600 hrs until approximately 1700 hrs.

MAY 11 - 2 CMBG: Z-101; 2 CMBG HQ & Sigs: H-119; 2 RCHA: P-113, P-114, P-115, P-115, Z-104, Z-105, Z-117, Z-120, Z-133, Z-649; 2 Svc Bn: H-110, H-112, K-101, K-102, L-1, L-108, L-54, L-57; 3 RCR: S-118; 4 Cdn Div TC: M-104; 4 CDSG Sig Sqn: H-101, L-109; Accommodations: J-103, J-108, L-101, L-103, L-104, P-101, P-50; B Foods: G-104; Gn Fire hall: S-665; Gn HQ: L-106, P-142, S-113; Gn HQ/RPOU/4 CDSG Sigs: S-111; Museum: P-51; OTHER: M-105, Z-106, Z-108, Z-608, Z-644, Z-684; PSP: J-106, L-105; and RPOU: P-49, S-114, S-124, S-41.

Temporary interruptions, lasting approximately 30 minutes at the commencement and conclusion of work, will affect the following buildings and complexes: 1 RCR: Y-101, Y-102; 2 CMBG HQ & Sigs: H-1; 2 MPU: N-104; 2 Svc Bn: D-104, D-105, D-106, D-107, D-55, D-57, D-623, D-624, D-625, D-9, H-104, H-114, H-118, H-120, H-121, H-16, H-619, H-621, H-622, H-645, H-646, O-104; 4 Cdn Div TC: H-107, H-124, N-107, O-9; 4 CDSG Sig Sqn: B-16, H-37, H-111;

Accommodations  F-16, G-101, G-102, G-106, N-103; CFJSR: O-106; Gn Fire Hall: AA-1, D-20; Gn Ops: B-21, C-104, Y-103, Y-104; OTHER: AA-20, AA-25, H-35, M-101, M-628, M-653, M-654, M-655, M-656, M-657, M-663, N-106; PSP: C-102, D-19, D-2; RCD: B-101, B-102, B-104, C-103, C-39, C-40, C-50, C-53, C-57, F-104, G-22; and RPOU: AA-19.

MAY 15 - 2 Fd Amb/Dental N-113; 2 MPU: 663-PT, P-123, P-57; DCC: P-144; Gn HQ / Gn MPs: P-105; Gn HQ / NPF: P-106; Gn HQ / PSP: Q-103; Gn HQ: Q-101, Q-104; Gn Ops / PSP: P-119; Gn Ops: P-141; JPSU: P-143; and PSP: P-117 (will be affected regardless of back-up generator), P-118, S-117.

MAY 17 - 2 Fd Amb/Dental N-113; 2 MPU: 663-PT, P-123, P-57; Accommodations: P-102; DCC: P-144; Gn HQ: Q-101, Q-104; Gn HQ / Gn MPs: P-105 (will be affected regardless of back-up generator); Gn HQ / NPF: P-106 (will be affected regardless of back-up generator); Gn HQ / PSP: Q-103; Gn Ops: P-141; Gn Ops / PSP: P-119; JPSU: P-143; and PSP: P-117, P-118 (will be affected regardless of back-up generator), S-117.

RP Ops creates detailed plans to minimize affected users, however occasionally unforeseen circumstances/emergencies may arise where buildings other than those identified may be affected. If there are any power outages at any areas or buildings outside of this list, please inform the RP Ops Det Petawawa Trouble Desk at local 5588 or the Duty Engineer after hours (via Grn Duty Officer x5611).

These power outages will not affect the RHUs.

POC: WO SC Mitchell, Works WO at local 6049.